> All that is needed is an option in the probit model to generate the
> Mills ratio as a post-estimation variable. I haven't checked whether it
> is there already but it could easily be added.
The Mills ratios are the generalised residuals in the probit case; hence,
you can access them as the probit residuals.
Riccardo (Jack) Lucchetti